Default A problem on men and work

Needed help to solve math home work problem

A can do 1/4 of a work in 10 days, B can do 40% of the work in 40 days and C can do 1/3 rd of the work in 13 days. If all three are working together, in how many day they can complete the total work?

Please tell me the procedure to solve the problem

Thanks
burgess is offline   Reply With Quote
Old 07-26-2014   #2
MAS1

Points: 8,254, Level: 61
Points: 8,254, Level: 61 Points: 8,254, Level: 61 Points: 8,254, Level: 61
Activity: 33.3%
Activity: 33.3% Activity: 33.3% Activity: 33.3%
Last Achievements
 
Join Date: Dec 2008
Posts: 249
Default

Quote:
Originally Posted by burgess View Post
Needed help to solve math home work problem

A can do 1/4 of a work in 10 days, B can do 40% of the work in 40 days and C can do 1/3 rd of the work in 13 days. If all three are working together, in how many day they can complete the total work?

Please tell me the procedure to solve the problem

Thanks
A: Since A can do 1/4 of the job in 10 days then it takes A 40 days to finish the job. A's rate of work is 1/40
B: Since B can do 2/5 of the job in 40 days then it takes B 100 days to finish the job. B's rate of work is 1/100
C:Since C can do 1/3 of the job in 13 days then it takes C 39 days to finish the job. C's rate of work is 1/39

We can add together the rtes and find a combined rate of work for A, B, and C.

1/40 + 1/100 + 1/39 = 0.025 + 0.01 + 0.025641... = .060641025641...

To find the number of days we take the reciprocal giving us about 16.5 days.
MAS1 is offline   Reply With Quote
Old 12-15-2014   #3
WilliamRVogl
 
Join Date: Dec 2014
Posts: 6
Default

All of them work in one day
A = 1/40
B = 1/100
C = 1/39
then the work will be completed in 16.49 days means 16 and 1/2 days.
WilliamRVogl is offline   Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump


All times are GMT -4. The time now is 10:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2017, vBulletin Solutions Inc.
XP Math